TEG Heavy Projects specialists successfully orchestrated the transportation of four gas purification sulfinox absorbers. The equipment was efficiently loaded onto a specialized heavy-lift vessel at Taicang Port, China, and dispatched to the transshipment port of Haydarpasha, Turkey. From there, the cargo was seamlessly transported via a river-sea barge through the Volga-Don Shipping Canal and into the Caspian Sea. Finally, the shipment was safely delivered to the construction site of the "Mustakillikning 25 yilligi" field for the construction of the Baysun Gas Processing Plant. The entire transportation process was completed in a remarkable 180 days.